Tadadi Port Project

KSIIDC as designated as the nodal agency for development of a Sea port at Tadadi on PPP basis. Following is the status of the project:

  • 1. KSIIDC has incorporated a special purpose company viz., “Tadadi Port Limited” paid up Capital – Rs. 5.00 lakhs

Status of Project

  • 1. About 1420 acres of land available for Port
  • 2. Detailed Feasibility Report (DFR) – prepared by Consortium of M/s Prointec (Spain) and M/s Mir Projects & Consultants
    • 1. Ultimate capacity of 62.36 mtpa (7 berths); Estimated project cost – Rs. 4318 crore (2017 rates). Master Plan is as shown below:
  • 3. EIA and CRZ Studies – by National Environment Engineering & Research Institute
    • 3a. CRZ clearance – Obtained
    • 3b. EIA report & also additional studies report submitted to MoEF & CC.
    • 3c. MoEF & CC – Environmental Clearance
    • a. Expert Appraisal Committee (EAC) has recommended for Environment Clearance with certain conditions (27 No’s), including Stage – I Forest Clearance & valuation of bivalves in the estuary region.
    • b. Study on valuation of bivalves – Department of Studies in Marine Biology, Karwar. Report is ready.
    • c. Stage – I Forest clearance for about 200 hectares of mangroves – awaited.
  • 4. Bid documents are under finalization by iDeCK (TA).

On obtaining forest and environmental clearances, tendering process (RFQ) will be initiated.